EMR Project Planning

Please do not modify
Page owner: Jackson
Sundance feb
Edmonton medical building, maybe by nov
- before christmas

Schedule

  • We assume each part time dev will work 16 hours / week.
    • 16 hours / week / dev = Mon(x) Tues(2) Wed(2) Thurs(2) Fri(2) Sat(8) Sun(x)
  • We also assume each full time dev will work 40 hours / week.

Milestones

September 30 (milestone 2)

  • Job posting for contract full time dev (Wendy & Jackson) by July 9th
  • Reception View (daily calendar) interface complete (Wendy)
    • Daily calendar (Wendy)
    • Patient demographics (Wendy)
    • Appointment search (Mike)
    • Patient search (Mike)
  • Prototypes of the Calendar View (Jackson) - 90% complete
  • Prototypes of the Chart View (Jackson) - 70% complete
  • Communication system design (Jackson)
  • Updated project schedule (Jackson & Wendy)

Oct 30 (milestone 3)

  • User log in / authentication, access levels
  • Hook up backend to calendar
  • Chart View interface
  • Communication window interface

Nov 29 (milestone 4)

  • Labs and radiology
  • Billing
  • Printing

Estimates

Recruiting

On Board

  • Jackson
    • project manager, product design, requirements / PO liason, usability, graphic design, dev
    • customer website design
    • logo
  • Wendy
    • tech lead, architecture, dev
  • Mike B
    • senior dev
  • Zaw A
    • dev

Declined

  • Somchay, JeffM, MarkM,

Potentials

  • VictorA, AndyL, NickW


 